The methodology of project management has been widespread in organizations of different functions and sizes. In this context, we address the issue of optimal resource allocation, and more specifically, the analysis of complementarity of resources (primary resource and supportive resource) in a project. We develop a conceptual system capable of determining the ideal timing, and the ideal mixture of resources allocated to the activities of a project, such that the project is completed on time, if not earlier, with minimal cost. In this paper we present new computational results of a Genetic Algorithm, based in a random keys alphabet to optimize the process to reach better results.