Analisis Performansi Pekerjaan Proyek Pembangunan Mechanical – Electrical – Pumbling Gedung Sentraland Semarang Menggunakan Metode Earned Value Analysis

机译:基于挣值分析法的Sentraland三宝垄机电翻新建筑施工项目工作绩效分析。

摘要

Projects generally have a time limit (deadline), meaning that the project must be completed before or right at a predetermined time. In construction projects Mechanical, Electrical, Plumbing (MEP) conducted by PT.Indospec, there is a lateness for 9 weeks, starting from week 44 through week 52, where at week 52 the plan percentage is at 87.40% and the actual percentage is at 33.53%. This makes the company feel the need to evaluate the performance of the project, in order to know the performance in completion of projects and the lateness factor, using Earned Value Analysis (EVA) and using Fault Tree Analysis (FTA). The results of the EVA calculation showed no increase of cost plans, but there is a delay in the completion time. Material Booked Unfinished, Late Delivery, No Warehouse, Cost Adjustment, Changes in Material, Changes in Functional, Architectural, Structural, a major cause in the lateness of the project. Good coordination and preparation of the project is very important in order to avoid lateness in the project.
机译:项目通常有时间限制(期限),这意味着项目必须在预定时间之前或恰好在预定时间完成。在PT.Indospec进行的机械,电气,管道工程(MEP)中,有一个为期9周的延迟,从第44周到第52周开始,在第52周,计划百分比为87.40%,而实际百分比为33.53%。这使公司感到需要评估项目的性能,以便使用盈余值分析(EVA)和故障树分析(FTA)来了解项目的完成情况和延迟因素。 EVA计算的结果表明,成本计划没有增加,但是完成时间有所延迟。预定的材料未完成,延迟交付,没有仓库,成本调整,材料更改,功能,建筑,结构的更改,这是项目延迟的主要原因。为了避免项目迟到,项目的良好协调和准备非常重要。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号