Specialist task organisations procurement approach for re-engineering construction project processes

机译:专门任务组织的采购方法,用于重新设计建设项目流程

摘要

This dissertation provides a framework for improving owners' contracting strategies through a specialist task organisations (STOs) procurement approach for re-engineering construction project processes. The aim of this dissertation is to develop a procurement system that improves an owner's project implementation process in order to meet the project objectives in terms of time, cost and quality. This study involves the analyses of the construction practices, processes, and procedures, the conditions of construction management (CM) contracts, the review of the theoretical bases, the design of a novel procurement method (STO), its initial validation in terms of the theoretical and empirical validation as well as conclusions and summary. The study reveals interrelationships between contracting practices, processes, procurement routes, payments, and risk allocation. The contracting practices of the USA, the UK, Japan and Finland are used as a frame of reference. The dissertation proposes a task-oriented approach to procurement through the integrated product (task) development, the integrated management and the fragmented execution via task organisations. The application area of the suggested STO route is limited to the project and procurement management of large building projects. The STO route allows an owner's design team to produce an overall design that is used by STOs to produce technical detailed engineering design solutions and project cost estimates. The validation of the suggested STO route has been carried out through the mapping against the organisation theories, the case-questionnaire results and the case study examples. These outcomes support the applicability of the STO. 35 case questionnaires were used to compare the prevailing procurement routes in relation to the suggested STO route. The four case examples provide some additional validation. The suggested merits of the STO route include the shift from only-single-designs and cost-based competition toward more advanced competition based on multiple designs, life-cycle costs, alternative materials, constructability and maintainability. The STO route assumes a modular approach to building design. It allows the use of experts' knowledge in design and construction through their involvement in all project stages.
机译:本论文通过专家任务组织(STO)的采购方法,为工程项目流程的重新设计提供了一个框架,以改善业主的合同策略。本文的目的是开发一种采购系统,以改善业主的项目实施过程,从而在时间,成本和质量上达到项目目标。这项研究包括对施工实践,过程和程序的分析,施工管理(CM)合同的条件,理论基础的回顾,新颖的采购方法(STO)的设计,其在采购方面的初步验证。理论和经验验证以及结论和总结。该研究揭示了订约实践,流程,采购路线,付款和风险分配之间的相互关系。美国,英国,日本和芬兰的合同惯例被用作参考框架。论文提出了一种面向任务的采购方法,通过集成的产品(任务)开发,集成的管理以及通过任务组织的零散执行来进行采购。建议的STO路线的应用范围仅限于大型建筑项目的项目和采购管理。 STO路线使业主的设计团队可以生成总体设计,供STO用来生成技术详细的工程设计解决方案和项目成本估算。通过对照组织理论,案例调查结果和案例研究示例进行映射,对建议的STO路线进行了验证。这些结果支持了STO的适用性。使用35个案例调查表比较了当前的采购路径与建议的STO路径。这四个案例提供了一些额外的验证。 STO路线的建议优点包括从单一设计和基于成本的竞争向基于多种设计,生命周期成本,替代材料,可施工性和可维护性的更高级竞争的转变。 STO路线采用模块化方法进行建筑设计。通过专家在所有项目阶段的参与,可以将其知识运用到设计和施工中。

著录项

  • 作者

    Oyegoke Adekunle Sabitu;

  • 作者单位
  • 年度 2007
  • 总页数
  • 原文格式 PDF
  • 正文语种 en
  • 中图分类

相似文献

  • 外文文献
  • 中文文献
  • 专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号