Stress Analysis and Testing at the Marshall Space Flight Center to Study Cause and Corrective Action of Space Shuttle External Tank Stringer Failures

机译:在马歇尔太空飞行中心进行应力分析和测试,以研究航天飞机外部油箱纵梁故障的原因和纠正措施

摘要

After the launch scrub of Space Shuttle mission STS-133 on November 5, 2010, large cracks were discovered in two of the External Tank intertank stringers. The NASA Marshall Space Flight Center, as managing center for the External Tank Project, coordinated the ensuing failure investigation and repair activities with several organizations, including the manufacturer, Lockheed Martin. To support the investigation, the Marshall Space Flight Center formed an ad-hoc stress analysis team to complement the efforts of Lockheed Martin. The team undertook six major efforts to analyze or test the structural behavior of the stringers. Extensive finite element modeling was performed to characterize the local stresses in the stringers near the region of failure. Data from a full-scale tanking test and from several subcomponent static load tests were used to confirm the analytical conclusions. The analysis and test activities of the team are summarized. The root cause of the stringer failures and the flight readiness rationale for the repairs that were implemented are discussed.
机译:在2010年11月5日航天飞机STS-133发射升空后,在两个“外部坦克”坦克中间纵梁上发现了大裂缝。 NASA马歇尔太空飞行中心作为外部坦克项目的管理中心,与包括制造商洛克希德·马丁公司在内的多个组织协调了随后的故障调查和维修活动。为了支持调查,马歇尔太空飞行中心成立了一个临时压力分析小组,以补充洛克希德·马丁公司的工作。该团队进行了六项主要工作,以分析或测试桁条的结构行为。进行了广泛的有限元建模,以表征失效区域附近纵梁中的局部应力。来自大规模油罐测试和几个子组件静载荷测试的数据用于确认分析结论。总结了团队的分析和测试活动。讨论了桁条失灵的根本原因以及进行维修的飞行准备理由。

著录项

  • 作者

    Wingate Robert J.;

  • 作者单位
  • 年度 2012
  • 总页数
  • 原文格式 PDF
  • 正文语种
  • 中图分类
  • 入库时间 2022-08-20 20:30:10

相似文献

  • 外文文献
  • 中文文献
  • 专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号