首页> 外文OA文献 >Identificación, evaluación y control de riesgos mecánicos en el proceso de construcción de sistemas de alcantarillado.
【2h】

Identificación, evaluación y control de riesgos mecánicos en el proceso de construcción de sistemas de alcantarillado.

机译:识别,评估和控制污水处理系统施工过程中的机械风险。

代理获取
本网站仅为用户提供外文OA文献查询和代理获取服务,本网站没有原文。下单后我们将采用程序或人工为您竭诚获取高质量的原文,但由于OA文献来源多样且变更频繁,仍可能出现获取不到、文献不完整或与标题不符等情况,如果获取不到我们将提供退款服务。请知悉。

摘要

The need to provide the population of Quito with basic services of potable water and sewage has forced the authorities to subcontract the needed infrastructure. In Quito, the EPMAPS, has an integrated management system, which establishes standards of security policy in the development of their activities and their subcontractors. Continuous improvement of that system and compliance with the national legislation implementing a Safety Management System and Health, has facilitated a starting point to identify and assess risks in the various mechanical processes that are part of the construction of Sewers Systems, in order to assess and estimate the mechanical risks of activities the personnel are most affected to through risk assessment techniques using the Fine Method and the NTP 330 Method, the results have demonstrated the high risk of working into ditches and activities happening at the same time at the trench edges, as well as the exposure of falls and entrapment by collapsing trench walls that workers can suffer; so it has been determined the need to define a protection mechanisms for the entire work force even at the beginning of the design stage.
机译:为基多人民提供饮用水和污水的基本服务的需求迫使当局将所需的基础设施分包出去。在基多,EPMAPS具有一个集成的管理系统,该系统在其活动及其分包商的发展中建立了安全策略的标准。该系统的不断改进以及对实施安全管理体系和健康的国家法规的遵守,为识别和评估下水道系统建设中各种机械过程中的风险提供了一个起点,以便评估和评估通过使用精细方法和NTP 330方法的风险评估技术,人员受到的活动的机械风险最大,结果表明,在沟渠边缘同时发生沟渠和活动的风险很高由于倒塌的沟渠墙而使工人容易遭受跌倒和夹带;因此,即使在设计阶段开始时,就已经确定需要为整个工作人员定义保护机制。