Heuristic procedures for reactive project scheduling

机译:响应式项目调度的启发式程序

摘要

This paper describes new heuristic reactive project scheduling procedures that may be used to repair resource-constrained roject baseline schedules that suer from multiple activity duration disruptions during project execution.The objective is to minimize the deviations between the baseline schedule and the schedule that is actually realized.We discuss computational results obtained with priority-rule based schedule generation schemes, a sampling approach and a weighted-earliness tardiness heuristic on a set of randomly generated project instances.
机译:本文介绍了新的启发式反应式项目计划程序,这些程序可用于修复在项目执行过程中因多个活动持续时间中断而受到资源限制的项目基准计划,目的是最大程度地减少基准计划与实际实现的计划之间的偏差我们讨论了基于随机规则的进度表生成方案,采样方法和加权早熟拖尾法对一组随机生成的项目实例所获得的计算结果。