Initial construction costs and net annual changes in operating and maintenance expenses are identified for a single-component capital renovation project proposed by Hidalgo County Irrigation District No. 1 to the Bureau of Reclamation and North American Development Bank. The proposed project involves installing 4.83 miles of multi-size pipeline to replace a segment of the North Branch / East Main canal. Both nominal and real estimates of water and energy savings and expected economic and financial costs of those savings are identified throughout the anticipated 48-year useful life for the proposed project. Sensitivity results for both the cost of water savings and cost of energy savings are presented for several important parameters.Annual water and energy savings forthcoming from the total project are estimated, using amortization procedures, to be 5,838 ac-ft of water per year and 3,293,049,926 BTUs (965,138 kwh) of energy per year. The calculated economic and financial cost of water savings is estimated to be $15.58 per ac-ft. The calculated economic and financial cost of energy savings is estimated at $0.0000392 per BTU ($0.134 per kwh).In addition, expected real (rather than nominal) values are indicated for the Bureau of Reclamation?s three principal evaluation measures specified in the United States Public Law 106-576 legislation. The initial construction cost per ac-ft of water savings measure is $30.68 per ac-ft of water savings. The initial construction cost per BTU (kwh) of energy savings measure is $0.0000544 per BTU ($0.186 per kwh). The ratio of initial construction costs per dollar of total annual economic savings is estimated to be -1.58.
机译:标识了伊达尔戈县第一灌溉区向垦殖局和北美开发银行提议的单项基本建设项目的初始建设成本以及运营和维护支出的年度净变化。拟议的项目包括安装4.83英里长的多尺寸管道,以替换北支/东干渠的一部分。可以在拟议项目的预期48年使用寿命中确定节水和能源节省的名义和实际估计以及这些节省的预期经济和财务成本。给出了几个重要参数的节水成本和节能成本的敏感性结果。使用摊销程序,整个项目每年的节水和节能量估计为每年5,838 ac-ft和3,293,049,926每年BTU(965,138千瓦时)的能源。计算得出的节水的经济和财务成本估计为每平方英尺15.58美元。计算得出的节能成本的经济和财务成本估计为每BTU 0.0000392美元(每千瓦时0.134美元)。此外,还为美国垦殖局指出了美国指定的三种主要评估措施的预期实际(而非标称)价值。公法106-576立法。每ac-ft节水量的初始建筑成本为$ 30.68 / acf。节能措施的每BTU(kwh)的初始建筑成本为每BTU 0.0000544美元(每千瓦时0.186美元)。每美元初始建设成本与每年总经济节约的比率估计为-1.58。

著录项

相似文献

  • 外文文献
  • 中文文献

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号