SCHEDULING CONSTRUCTION PROJECTS WITH RESOURCES ACCESSIBILITY LIMITED AND CHANGEABLE IN TIME

机译:调度建设项目具有资源可访问性有限和可变的时间

代理获取
本网站仅为用户提供外文OA文献查询和代理获取服务,本网站没有原文。下单后我们将采用程序或人工为您竭诚获取高质量的原文,但由于OA文献来源多样且变更频繁,仍可能出现获取不到、文献不完整或与标题不符等情况,如果获取不到我们将提供退款服务。请知悉。

摘要

This paper aims at solving the problem of minimising the construction project duration in deterministic conditions when the accessibility of renewable resources is limited and changeable in time (workforce, machines and equipment). Particular construction processes (with various levels of complexity) must be conducted in the established technological order and can be executed in different technological and organisational variants (different contractors, technologies, and ways of using resources). To solve this problem the authors are using evolutionary algorithm. For the assessment of solutions generated by evolutionary algorithm, the authors have worked out a heuristic algorithm (of resources allocation and project duration calculation). This methodology seems to produce similar outcomes when juxtaposed with other solutions obtained by research works carried out using comparable methodologies. The paper contains an example of practical application of evolutionary algorithm for construction project planning within resources and time constraints.First Published Online: 14 Oct 2010
机译:本文旨在解决在可再生资源的可访问性有限且可变的时间(劳动力,机器和设备)有限和可变时最小化确定性条件下的建筑项目持续时间的问题。必须以既定的技术秩序进行特定的施工过程(具有各种级别的复杂性),可以以不同的技术和组织变体(不同的承包商,技术和使用资源方式)执行。为了解决这个问题,作者正在使用进化算法。对于评估进化算法产生的解决方案,作者已经制定了一种启发式算法(资源分配和项目持续时间计算)。当与通过使用可比方法进行的研究工程所获得的其他解决方案并置时,该方法似乎产生了类似的结果。本文包含资源和时间限制内建设项目规划进化算法的实际应用示例。首次出版在线:2010年10月14日

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
代理获取

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号