首页> 美国政府科技报告 >Turbine Performance Test - Unit G24. Grand Coulee Dam, Grand Coulee Third Powerplant, Columbia Basin Project. Flow Measurement by the Pressure-time Method
【24h】

Turbine Performance Test - Unit G24. Grand Coulee Dam, Grand Coulee Third Powerplant, Columbia Basin Project. Flow Measurement by the Pressure-time Method

机译:涡轮性能测试 - G24单元。 Grand Coulee Dam,Grand Coulee第三发电厂,哥伦比亚盆地项目。压力 - 时间法测量流量

获取原文

摘要

A performance test was conducted June 7 to 9, 1983, on the vertical-shaft, Francis turbine at Grand Coulee Third Powerplant, Grand Coulee Dam, Washington. Operating characteristics were determined: i.e., horsepower, discharge, efficiency, and flow index calibrations.