首页> 美国政府科技报告 >Cathodic Protection of U.S. 15 Over Lycoming Creek at Hepburnville, Pennsylvania.Cathodic Deck Protection and Latex Modified Concrete Overlay on Steel I-Beam Bridge
【24h】

Cathodic Protection of U.S. 15 Over Lycoming Creek at Hepburnville, Pennsylvania.Cathodic Deck Protection and Latex Modified Concrete Overlay on Steel I-Beam Bridge

机译:在宾夕法尼亚州Hepburnville的Lycoming Creek的美国15号阴极保护。钢工字梁桥上的阴极甲板保护和乳胶改性混凝土覆盖层

获取原文

摘要

The report describes the condition of the reinforced concrete deck at the time ofits rehabilitation, documents the rehabilitation specifications and the actual construction, and details the monitoring procedures that will be used to verify the functional adequacy of the cathodic protection. The cathodic protection system was applied to the patched and scarified bridge deck. The deck was then blast cleaned and a 1-1/2 inch thick latex modified concrete wearing surface placed. The constant current cathodic protection system consisted of approximately 9,700 sq ft of Raychem Ferex 100 anode, a prefabricated conductive polymer mesh. The four (4) zone impressed current system is powered by a multiple output rectifier and monitored with silver/silver chloride reference electrodes and re-bar probes. Traffic was maintained on one lane while the adjacent lane was under construction.

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号