Hanford Engineer Works monthly report, June 1946.

机译:汉福德工程师工作月刊,1946年6月。

获取原文

摘要

This progress report discusses activities at Hanford Engineer Works for the month of June 1946. On June 4 the Plant completed 143 days without a time losing injury and became eligible for the General Manager's Safety Award. A suitable prize is being presented to each employee. The month of June was successful from the standpoint of safety and as of month end 166 safe days had been accumulated. The 100 D and 100 F Areas operated at power levels of 250 megawatts (MW) and 200 MW respectively. Scheduled shutdowns for routine maintenance and metal discharge were taken. Overall operating time efficiency was 84.5% and is low because the replacement of the No. 9 horizontal rod thimble at D required 86 hours. Operating schedules in the Separations Plant were adjusted to process discharged metal from the 100 Areas. A 60 day ''cooling'' period was maintained. Fifty-seven charges were started through the Canyon Buildings and 64 were delivered from the Isolation Building. B Plant was down for 6 days during the month due to a failure in a metal waste line which caused an appreciable cave-in adjacent to the Canyon Building. After testing the spare lines, operations were resumed and steps have been taken to correct the fault. Representatives of the General Electric Company arrived on the project on June 17 to make preliminary arrangements for their acceptance of operating responsibility as the new contractor. The entire period was spent in interviewing personnel both individually and in groups.

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号