Low-Head Hydroelectric Power Demonstration Project: City of Gonzales, Texas. Final Technical and Construction Cost Report

机译:低水头水力发电示范项目:德克萨斯州冈萨雷斯市。最终技术和施工成本报告

获取原文

摘要

This project involved the restoration of a hydroelectric power plant and dam facility in Gonzales, Texas. The task was to dismantle and refurbish three existing turbines and to install new generators and electrical equipment. The awarding of contracts and costs of each piece of equipment are briefly discussed. After testing and additional adjustments the turbine efficiency was held between 7.4 and 10.1% below guaranteed output levels, yet a problem still remained in braking the turbines to a complete stop. (ERA citation 10:025401)