The scheduled 58-day refueling outage in preparation for the seventh operating cycle of the Fast Flux Test Facility (FFTF) was successfully completed three days ahead of schedule. The planning and execution of the outage was greatly aided by Project/2 automated scheduling capabilities. For example, the use of ''maintenance windows'' and resource loading capabilities was particularly effective. The value of the planning process was demonstrated by the smooth transition into the outage phase after an early shutdown and set the stage for our best outage to date. (ERA citation 12:000434)