Tata Steel's blast furnace 'G' upgrade--design concept, project development and operating results

机译:塔塔钢铁公司的高炉“ G”升级-设计理念,项目开发和运营成果

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

In April 2005, the upgraded blast furnace "G" of Tata Steel was blown in after a four-months shutdown in which it was rebuilt on the existing foundation. Despite several plant constraints, it was possible to increase the furnace working volume by 45 percent. The project covered significant interventions: on the stockhouse, top charging system, furnace cooling system, casthouse, slag granulation, PCI, blast system, and gas cleaning, to cope up with the changed operating conditions. In this paper the key points of the design, the project development and a summary of the operating results are presented.
机译:2005年4月,塔塔钢铁公司升级后的高炉“ G”在停工四个月后被吹入,并在现有基础上进行了重建。尽管工厂受到了一些限制,但仍有可能将熔炉的工作量提高45%。该项目涵盖了重要的干预措施:在仓库,顶部装料系统,熔炉冷却系统,铸造车间,炉渣造粒,PCI,鼓风系统和气体清洁方面,以应对变化的运行条件。本文介绍了设计的关键点,项目开发以及运营结果摘要。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号