This 10.8 million dollars modernization of Fay Herron Elementary School in North Las Vegas was completed in July. The 916-student public school teaches grades K-5. The project reduces annual energy demands at the aging 44-year-old, 61,801-sq-ft school complex by 80 tons for a 49 percent cost savings. The feat was achieved by installing a highly-efficient, prefabricated central chiller and boiler plant with a new four-pipe chilled water and hot water piping system. Individual multi-zone air handlers with roof-mounted refrigeration units were placed atop roofs of the 12-building campus while exterior and interior wall insulation and heavy-duty doors were added.
机译:这项耗资1080万美元的现代化改造工程在北拉斯维加斯的费伊·赫伦小学于七月完成。拥有916名学生的公立学校教授K-5年级。该项目将拥有44年历史,占地61,801平方英尺的老校舍的年度能源需求减少了80吨,节省了49%的成本。这一壮举是通过安装高效,预制的中央冷却器和锅炉设备以及新的四管冷冻水和热水管道系统实现的。带有顶棚制冷单元的各个多区域空气处理机被放置在12栋大楼校园的屋顶上,同时增加了外墙和内墙隔热层以及重型门。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号