Hylsa commissioned its new flat products mill in February 1995. It consists of a DC electric arc furnace, an AC ladle metallurgy furnace, a CSP caster and a 6-stand hot strip mill which can produce strip in widths up to 1 350 mm and thicknesses between 1.0 and 12.7 mm. Production up to October 1995 was over 200 000 t. The breakout rate was only 0.3 percent, the casting sequence incorporating up to 11 heats with prime quality up to 98 percent. These results are better than the projected values, with a total work force of only 280 people.
机译:Hylsa于1995年2月启用了其新的扁平产品轧机。该轧机包括直流电弧炉,交流钢包冶金炉,CSP连铸机和6机架热轧机,该轧机可以生产宽度最大为1 350 mm的板条在1.0和12.7毫米之间到1995年10月,产量超过20万吨。破损率仅为0.3%,浇铸顺序可合并多达11道钢水,其主要品质可达98%。这些结果比预期的结果要好,总共只有280人。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号