TransCanada Corp. has raised the cost estimate of the beleaguered Keystone XL pipeline expansion by US$1 billion to $13 billion and said it expects regulatory delays. According to a February 15 statement, the Calgary-based pipeline company increased capital expenditure estimates, because the necessary regulatory decisions for the pipeline project are not expected until "mid-tolate 2011," and cited a "heightened political environment" and opposition to the project. "The revised capital cost estimate reflects currency translation, higher than anticipated costs to complete the first two phases of the project and an increase in the estimated cost of completing the U.S. Gulf Coast Expansion as a result of scope changes, evolving regulatory requirements and permitting delays," the statement reads.
机译:TransCanada Corp.已将陷入困境的Keystone XL管道扩建的成本估算提高了10亿美元,至130亿美元,并表示预计监管将延迟。根据2月15日的声明,这家位于卡尔加里的管道公司提高了资本支出估算值,因为该管道项目的必要监管决定预计要到2011年中旬才会出现,并引述了“政治环境加剧”和反对项目。 “修订后的资本成本估算反映了货币换算,完成项目前两个阶段的成本高于预期,以及由于范围变更,法规要求不断变化和允许延迟而导致完成美国墨西哥湾沿岸扩张的估算成本的增加,该语句显示为。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号