Tegni Cymru Cyf v Welsh Ministers and Denbighshire County Council [2010] EWHC 1106 (Admin) concerns proposals to build 13 turbines of 125m height on an upland area within Clocaenog Forest in Denbighshire and the refusal of planning permission on the basis of the noise impact. On 13 May 2007 Tegni Cymru Cyf, the Claimant, made an application for planning permission to construct 13 wind turbine generators together with associated infrastructure. The application sought permission to construct generators up to 125 metres in overall height; it predicted that the overall capacity of the generators would be between 32 and 39.5 MW and that the generators would power approximately 23,896 homes.
机译:Tegni Cymru Cyf诉威尔士部长和Denbighshire县议会[2010] EWHC 1106(Admin)涉及在Denbighshire的Clocaenog森林内的高地地区建造13台125m高涡轮机的建议,以及基于噪声影响而拒绝规划许可的建议。 2007年5月13日,索赔人Tegni Cymru Cyf提出了计划许可申请,以建造13台风力涡轮发电机以及相关的基础设施。该申请寻求建造总高度不超过125米的发电机的许可;它预测发电机的总容量将在32至39.5 MW之间,并且发电机将为大约23,896户家庭供电。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号