The purpose of Lesotho Highlands Water Project isprimarily to supply water from Lesotho to Gauteng Province, theindustrial region of South Africa. In addition, the hydroelectricscheme at Muela will supply enough electrical power to meet theneeds of Lesotho. The project consists of a number of dams,reservoirs and tunnels, and a hydroelectric scheme which will beconstructed in four phases. Construction operations, if the projectruns to completion, will last until around 2020. Phase IAcommenced in 1987 and consists of Katse Dam, a Transfer Tunnelfrom the impounded reservoir to the Muela Hydroelectric PowerStation, the Muela Dam, and a Delivery Tunnel from the latter damto the outfall on the Ash River, which is part of the Vaal Riversystem. The tunnels total some 81 km in length. Except for theadits which were drilled and blasted, the tunnels were constructedby five tunnel boring machines.The Katse Dam and Transfer Tunnel were constructed in thebasalts of the Drakensberg Formation. Many of these basalts havebeen subjected to deuteric alteration and consequently containexpansive clay minerals. Their presence can mean that the basaltsdisintegrate rapidly on exposure, which led to increased excavationat the dam site, and slab-bing and spalling from the perimeter ofthe tunnel. The Muela Hydroelectric Power Station and DeliveryTunnel South were constructed primarily in sandstones of theClarens Formation. These sand. stones presented few problemsduring excavation and this tunnel was bored 20 months ahead ofschedule. It was anticipated that the Delivery Tunnel North wouldbe the most difficult to excavate as it runs through a succession ofmudstones and sandstones. Hence, this tunnel was excavated by adouble-shielded tunnel boring machine which could bore throughvaried ground and provide protection against rock fall, whilesimultaneously installing precast lining segments.
机译:莱索托高地水项目的目的主要是从莱索托向南非工业区豪登省供水。此外,穆埃拉(Muela)的水电项目将提供足够的电力,以满足莱索托的需求。该项目包括许多水坝,水库和隧道,以及将分四个阶段进行建设的水力发电计划。如果该项目完成,则建设运营将持续到2020年左右。IA期于1987年开始运营,包括Katse大坝,从蓄水库到Muela水力发电站的转运隧道,Muela大坝以及从后者的大坝到水库的出水隧道。瓦尔河系统的一部分-阿什河上的水流。隧道全长约81公里。除了钻进和爆破外,隧道是由五台隧道掘进机建造的。凯瑟斯大坝和中转隧道是在德拉肯斯堡组的玄武岩中建造的。这些玄武岩中的许多已经经历了氘代蚀变,因此含有膨胀的粘土矿物。它们的存在可能意味着玄武岩在暴露时会迅速崩解,从而导致在坝址处的开挖增加,并从隧道周围剥落和剥落。穆埃拉水电站和南输水隧道主要建在克拉伦斯组的砂岩中。这些沙子。石头在开挖过程中几乎没有问题,该隧道比原计划提前了20个月。可以预料的是,北输送隧道贯穿连续的泥岩和砂岩时,将是最难开挖的。因此,该隧道是由双屏蔽隧道掘进机开挖的,该掘进机可以钻通各种地面并提供防岩落保护,同时安装预制衬砌段。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号