The ultimate depth of a scour pit downstream of a debris flow sabo dam is an important design parameter in determining the foundation bearing depth of a debris flow for Sabo dam. This paper considers the scour pit system as a black box, neglecting the energy consumed by inter-particle collision of debris flow and the collision between debris flow and the valley bed. A formula was developed for the ultimate depth of a scour pit using the energy method to establish debris flow energy changes in and out of scour pit, combined with the energy needed by sediment incipient. When the results of the formula are compared with a series of indoor flume experiments, the error ranged from 3.1% to 17.6%. The calculated and experimental values agreed well, indicating that the method based on the energy method is reasonable and feasible.
机译:泥石流Sabo坝下游的冲刷坑的最终深度是确定Sabo坝泥石流基础承载深度的重要设计参数。本文认为冲刷坑系统是一个黑匣子,忽略了泥石流的颗粒间碰撞以及泥石流与山谷床之间的碰撞所消耗的能量。使用能量方法开发了冲刷坑的最终深度的公式,以建立冲刷坑内和冲刷坑外的泥石流能量变化,并结合沉积初期所需的能量。将配方的结果与一系列室内水槽实验进行比较时,误差范围为3.1%至17.6%。计算结果与实验值吻合良好,表明基于能量法的方法是合理可行的。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号