首页> 外文期刊>Engineering & Mining Journal >Telfer Redevelopment Running Ahead of Schedule
【24h】

Telfer Redevelopment Running Ahead of Schedule

机译:Telfer重建计划提前完成

获取原文
获取原文并翻译 | 示例

摘要

Newcrest Mining reported in early October that its massive, 1.2-billion Australia dollars Telfer open pit-underground gold-copper redevelopment project in Western Australia was 49 percent complete and ahead of schedule. Project completion, originally slated for September 2004, could be achieved as early as May or June. Newcrest is Australia's largest listed gold producer, with current production of 780,000 ounces per year. Telfer production of around 800,000 oz per year will slightly more than double that total. Telfer will also add some 30,000 mt per year of copper to Newcrest's production totals. Open-pit equipment commissioned at Telfer as of the end of September included a shovel, three excavators, 11 trucks, and support equipment. An additional three trucks are due for delivery in December. Construction of the open pit mobile equipment service station, high voltage reticulation, water pipelines, and heavy duty workshop were well advanced, with the majority of these items on schedule for completion before year-end. Some 14 million mt of waste material had been moved at productivity and costs better than feasibility study estimates. Construction of the tailings storage facility using open pit waste was well advanced.
机译:Newcrest Mining在10月初报道说,其在西澳大利亚的价值12亿澳元的Telfer露天金矿-地下金-铜重建项目已完成49%,比计划提前。该项目原定于2004年9月完成,最早可在5月或6月完成。 Newcrest是澳大利亚最大的上市黄金生产商,目前的年产量为780,000盎司。 Telfer的年产量约为80万盎司,将是总产量的两倍多。 Telfer还将每年在Newcrest的总产量中增加约30,000吨铜。截至9月底,在Telfer调试的露天设备包括铁锹,三台挖掘机,11辆卡车和辅助设备。另有三辆卡车将于12月交付。露天移动设备服务站,高压网状结构,输水管道和重型车间的建设进展顺利,其中大部分项目如期完工,预计于年底前完工。约有1400万吨的废料以生产率和成本进行了运输,其成本高于可行性研究的估计值。利用露天废料建设尾矿储存设施的工作进展顺利。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号