Weirton tandem cold mill fire recovery project

机译:威顿串联冷轧机火灾恢复项目

获取原文
获取原文并翻译 | 示例
       

摘要

All mechanical, electrical and hydraulic equipment on a 5-stand cold reduction mill as well as the building and roof were severely damaged or destroyed by a major fire. A fast-track project, involving the company's personnel, suppliers and contractors, was established: rolling operations were resumed after approximately six months.
机译:五站式冷轧机上的所有机械,电气和液压设备以及建筑物和屋顶都被大火严重损坏或破坏。建立了一个涉及公司人员,供应商和承包商的快速项目:大约六个月后恢复了轧制作业。