Scheduling with sequence-dependent batch setup times: planning tests for a pharmaceutic industry

机译:计划与序列相关的批次设置时间:制药行业的计划测试

获取原文
获取原文并翻译 | 示例
       

摘要

In this work, we propose an approach for a real sequence-dependent batch setup times scheduling problem arising in a pharmaceutical company. A legal obligation for the pharmaceutical industry is to monitor the quality of their products during its life cycle. The development of new pharmaceutical products (medicines) leads to a high number of batches to be tested in order to accomplish with certain regulatory obligations regarding maintaining safeguards on quality and safety. The time lines are critical in this process. The problem is how to manage and schedule a number of tests, that require setups and obey to certain precedence relations, to avoid delays in the answers.
机译:在这项工作中,我们提出了一种解决实际问题的方法,该方法取决于制药公司中出现的与序列有关的批次设置时间调度问题。制药行业的法律义务是在其生命周期内监视其产品质量。新药品(药品)的开发导致要进行大量测试的批次,以便在维护质量和安全保障方面履行某些监管义务。时间线在这个过程中至关重要。问题是如何管理和安排许多测试,这些测试需要进行设置并遵守某些优先顺序,以避免延误答案。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号