Sabine Pass completion rate ahead of schedule

机译:沙宾通票提前完成率

获取原文
获取原文并翻译 | 示例
           

摘要

US firm Cheniere Energy completed 37.6pc of the planned first two liquefaction trains at its Sabine Pass export project in Louisiana as of 30 June, slightly ahead of the planned 34.7pc completion rate, it said on 19 July. The first and second trains are on schedule to be substantially completed by February 2016 and June 2016, respectively. Cheniere previously told Argus that the first send-out cargo for each train is expected about three months before each of those completion dates. The third and fourth trains are due to start operating in 2016-17. Each train will have capacity of 4.5mn t/yr, equivalent to 16mn m~3/d of pipeline gas (AGL, June, p18).
机译:美国公司Cheniere Energy于7月19日表示,截至6月30日,其路易斯安那州Sabine Pass出口项目已完成计划的前两批液化火车的37.6%,略高于计划的34.7%的完成率。第一列和第二列列车如期分别于2016年2月和2016年6月完成。 Cheniere先前告诉Argus,每列火车的首批送出货物预计在每个完工日期之前三个月左右。第三和第四列火车将于2016-17年开始运营。每列火车的产能为450万吨/年,相当于1600万立方米/天/天的管道气(AGL,6月,第18页)。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号