Design and construction of SEMABUCHI VIADUCT

机译:SEMABUCHI VIADUCT的设计与施工

获取原文
获取原文并翻译 | 示例

摘要

SEMABUCHI VIADUCT is a 4 span continuous composite bridge with 2 main I-shaped girders and pre-stressed concrete (PC) slab which is cast in site using movable forming equipment. Recently a few bridges with a few girders and PC slab are constructed. The bridge is rationalized by using PC slab which has higher duration than reinforced concrete slab and using composite design in which slab is effective as main girder section with steel girders. Rationalized design for steel girders and omission of temporary assembly in works decreased fabricating labor and time. On the other hand movable forming equipment rationalized making PC slab with cyclic casting. SHI designed and manufactured new movable forming equipment for this site.
机译:濑武至高架桥是一座4跨度的连续组合桥,有2根工字主梁和预应力混凝土(PC)板,使用可移动成型设备在现场浇筑。最近建造了几座带有几根大梁和PC板的桥梁。该桥采用比钢筋混凝土板工期长的PC板,并采用复合设计,其中板与钢梁作为主梁截面有效。钢梁的合理化设计,以及工程中临时装配的省略,减少了制造劳动力和时间。另一方面,可移动成型设备合理化,采用循环铸造制造PC板坯。SHI为该工厂设计并制造了新的可移动成型设备。

著录项

获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号