3D Numerical Investigation of Ground Settlements Induced by Construction of Istanbul Twin Metro Tunnels with Special Focus on Tunnel Spacing

机译:3D伊斯坦布尔双地铁隧道施工地面定居点的数值调查与隧道间距专注于隧道间距

获取原文
获取原文并翻译 | 示例
       

摘要

One of the most important considerations of tunneling in urban areas is controlling the amount of surface settlement that occurs during construction stages. The goal of this paper is to investigate the effect of spacing of Istanbul Twin Metro Tunnels on the surface settlement excavated by NATM method in YENIKAPI-UNKAPANI metro line. For this purpose, the focus has been placed on the effect of longitudinal and transversal spacing between tunnels supported by an umbrella arch protecting method. (FLAC3D) was implemented to simulate the excavation sequence. According to the analysis, the amount of settlement by numerical approach was about 23.5 mm which was in good agreement with the field monitoring results that was 26.5 mm. Moreover, the interaction between twin tunnels by the increase in spacing between twin tunnels in the direction perpendicular to tunnel axis decreases and becomes less effective at the location about 3 times of the tunnel diameter. Similarly, the interaction between twin tunnels in the direction parallel to tunnel axis decreases as the spacing increases. In other words, by increasing the distance between tunnel faces in longitudinal direction at a distance about 3 times of the tunnel diameter, there is still interaction between tunnels and it doesn't disappear completely. Therefore, it is recommended to keep this distance at about more than 2.5 times of tunnel diameter so that settlement can stay within acceptable range.
机译:城市地区隧道施工最重要的考虑因素之一是控制施工阶段出现的地表沉降量。本文旨在研究伊斯坦布尔双隧道间距对YENIKAPI-UNKAPANI地铁线路新奥法开挖地表沉降的影响。为此,重点研究了伞形拱保护法支撑的隧道之间纵向和横向间距的影响。(FLAC3D)用于模拟开挖顺序。根据分析,通过数值方法得出的沉降量约为23.5mm,与现场监测结果26.5mm一致。此外,在垂直于隧道轴线的方向上,通过增加两个隧道之间的间距,两个隧道之间的相互作用减小,并且在隧道直径约3倍的位置处变得不那么有效。同样,平行于隧道轴线方向的双隧道之间的相互作用随着间距的增加而减小。换句话说,通过在隧道直径的3倍左右的距离上增加纵向隧道面之间的距离,隧道之间仍然存在相互作用,并且不会完全消失。因此,建议将该距离保持在隧道直径的2.5倍以上,以便沉降保持在可接受范围内。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号