Drax extends planned 2019, 2021 outages

机译:Drax延伸计划2019年,2021个中断

获取原文
获取原文并翻译 | 示例

摘要

UK utility Drax has extended a planned outage at its 645MW wood pellet-fired unit 2 at its power plant in Selby, North Yorkshire, by 18 days. The unit will now be off line for almost 81 days from 11 July-30 September 2019, during which time turbine upgrade work will take place. It was previously set to be shut down for 63 days, from 11 July-12 September 2019.