Quantitative appraisal of cost and time performance of construction projects in public and private universities in Osun State, Nigeria

机译:尼日利亚奥伦州公共和私立大学建设项目成本和时间绩效的定量评价

获取原文
获取原文并翻译 | 示例
           

摘要

Purpose - The purpose of this paper is to compare the cost and time performance of construction projects in public and private universities in Osun State, Nigeria. Design/methodology/approach - Purposive sampling technique was adopted to select four universities (two public and two private) used for the study. Archival data on 40 completed construction projects (ten from each university) was used in the study. Data were analysed with percentile and t-test. Findings - The study showed that only 35 per cent of the construction projects in public and 10 per cent of those in private universities were completed at the estimated cost. There were no construction projects completed within the planned time in public universities, but 20 per cent were completed within the planned time in private universities. The t-test showed there is no significant difference in performance of construction projects in public and private universities in Nigeria. The study concluded that time performance of public and private universities in Nigeria was still below acceptable international best practices. Research limitations/implications - The findings of this study are limited to universities' construction projects and may be of little application to other construction projects outside university settings. Practical implications - It is recommended that construction stakeholders be more proactive in ensuring that significant improvement is achieved in cost and time performance of construction projects both in public and private universities; the clients need to be more detailed in their briefs and requirements, the designers (architects and engineers) need to be more precise and avoid varying their designs, the quantity surveyors should use their professional competency in cost engineering adequately and the contractor should avoid spurious claims that result in increase in construction cost and time so that performance of construction projects can be improved. Originality/value - The study is an attempt to compare cost and time performance of construction projects in public and private universities in Osun State, Nigeria.
机译:目的 - 本文的目的是比较尼日利亚奥伦州公共和私立大学建设项目的成本和时间绩效。采用设计/方法/方法 - 采用目的地采样技术选择用于该研究的四所大学(两个公共和两个私人)。在研究中使用了40个已完成的建筑项目的档案数据(每所大学十个)。用百分位和T检验分析数据。研究结果 - 该研究表明,公共设施只有35%,私立大学的10%以估计的成本完成。在公立大学的计划时间内没有完成建筑项目,但在私立大学的计划时间内完成了20%。 T检验表明,尼日利亚公共和私立大学的建设项目表现没有显着差异。该研究得出结论,尼日利亚公共和私立大学的时间绩效仍低于可接受的国际最佳实践。研究限制/影响 - 本研究的结果仅限于大学的建设项目,并且可能对大学环境外的其他建筑项目的应用很少。实际意义 - 建议建设利益攸关方在确保公共和私立大学的建筑项目的成本和时间绩效中取得了重大改善;客户需要更详细地进行简介和要求,设计人员(建筑师和工程师)需要更加精确,避免改变其设计,数量测量师应充分地使用其专业能力,并承包商应避免虚假索赔这导致施工成本和时间增加,以便可以提高建筑项目的性能。原创性/价值 - 该研究是一种试图比较尼日利亚奥伦州公共和私立大学建设项目的成本和时间绩效。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号