首页> 外文期刊>Corrosion & Materials >WHAT'S RUSTINGS - Tacoma Bridge Opening Delayed Three Months
【24h】

WHAT'S RUSTINGS - Tacoma Bridge Opening Delayed Three Months

机译:烦恼-塔科马大桥的开放时间推迟了三个月

获取原文
获取原文并翻译 | 示例
           

摘要

The Seattle Times reported recently that the new Tacoma Narrows Bridge will open three months late, in July 2007, according to the State of Washington. Delays are blamed mainly on corroded wires discovered in November. Contractors had to replace about a third of the Korean-made wire spools, which had been stored outdoors on the Tacoma side of the waterway. The corrosion was caused by a wrapping paper that reacted chemically with the steel wires when wet, forming a white powder, said Claudia Cornish, spokeswoman for the Washington state Department of Transportation.
机译:据华盛顿州报道,《西雅图时报》最近报道说,新的塔科马海峡大桥将于2007年7月推迟开放三个月。延误主要归因于11月发现的锈蚀电线。承包商不得不更换约三分之一的韩国制造的线轴,这些线轴存储在水路塔科马一侧的室外。华盛顿州交通部发言人克劳迪娅·康尼什(Claudia Cornish)表示,腐蚀是由包装纸引起的,该包装纸在潮湿时会与钢丝发生化学反应,形成白色粉末。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号