Overcoming the Problem of 101-C Tube Bundle Lifting by Modifying the Lifting System in Ammonia Plant

机译:通过改变氨植物的提升系统来克服101-C管束提升的问题

获取原文
获取原文并翻译 | 示例
           

摘要

At KRIBHCO ammonia plant, secondary waste heat exchanger (102-C) top dome bend was obstructing the lateral shifting of primary waste heater exchanger (101-CB) tube bundle over 102-C, whenever 101-CB tube bundle is replaced. To allow the shifting of 101-CB tube bundle above the 102-C, we were making required room by removing 102-C dome cover. This 102-C dome cover opening, box up and gasket replacement job was resulting in increased maintenance cost & job duration. To overcome the problem, existing 40-T capacity 101-C tube bundle lifting system was modified to gain the lifting margin required for shifting of 101-CB bundle above 102-C without removing its dome cover. The complete modification job including design & fabrication of required items was carried through internal resources.
机译:在Kribhco氨植物,次级垃圾换热器(102-C)顶部圆顶弯曲堵塞初级废料加热器交换器(101-CB)管束上的横向移位,每当101-CB管束被更换时,每当101 CB管束被替换。 为了允许在102-C上方移位101-CB管束,我们通过去除102-C圆顶盖进行所需的空间。 这款102-C圆顶盖开口,盒子和垫片更换工作导致维护成本和工作持续时间增加。 为了克服该问题,修改了现有的40-T容量101-C管束升降系统以增强101-CB束以上102-C以上的升降裕度而不移除其圆顶盖。 完整的修改工作包括所需物品的设计和制造,通过内部资源进行。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号