Carbon fibre hoops hasten repair of fertilizer tower

机译:碳纤维箍加快化肥塔维修

获取原文
获取原文并翻译 | 示例

摘要

Hoops of carbon fibre reinforced plastic (CFRP) plates have saved 70 extra days of shutdown on a urea prill tower at Qatar Fertiliser Co (QAFCO).UK consultant Mouchel, which advised on the project, says that the 65m high, slip-form concrete tower was strengthened with 3500 m of bonded CFRP plates in just 20 days, instead of the 90 days that would have been needed to carry out the job using steel or concrete.Constructed 30 years ago, the tower is a critical part of the QAFCO's process stream and produces 400 kt of urea fertilizer prills a year. When spalling faults and cracks appeared in the 380 mm thick wall, Mouchel structural repair experts were appointed to assess the problem and specify remedial measures that would minimize business disruption.
机译:卡塔尔肥料公司(QAFCO)的尿素造粒塔用碳纤维增强塑料(CFRP)板箍节省了70多天的停机时间。为该项目提供建议的英国顾问Mouchel说,该65m高的滑模混凝土在短短20天内,用3500 m的CFRP板加固了铁塔,而不是用钢或混凝土完成工作所需的90天。30年前建造的铁塔是QAFCO流程的关键部分每年可生产400 kt尿素肥料颗粒。当380毫米厚的墙壁出现剥落的断层和裂缝时,Mouchel结构维修专家被任命来评估问题并指定补救措施,以最大程度地减少业务中断。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号