A major Greek court ruling has put the final nail in the coffin for planned power plant Meliti II and left its sister plant Meliti I operating without legal permission. The decision follows a legal challenge brought jointly by ClientEarth, WWF Greece and Greenpeace Greece. Greece's Supreme Administrative Court, the Greek Council of State, annulled the environmental permits for the two lignite-fired power plants, both property of state power company PPC.The decision means that the construction of Meliti II will no longer go ahead, while Meliti I will need to apply for a new environmental permit if it is to continue operating.
展开▼
机译:一家主要的希腊法院裁决将最后的钉子放在棺材中为计划发电厂Meliti II,并在没有法律许可的情况下离开了其姐妹植物梅利蒂。 该决定遵循Clientearth,WWF希腊和GreenPeace希腊共同带来的法律挑战。 希腊最高行政法院是希腊国务院的,取消了两个褐煤发电厂的环境许可证,这是国家电力公司PPC的财产。决定意味着Meliti II的建设将不再前进,而Meliti I 如果继续运营,需要申请新的环境许可证。