Comparison of Earned Schedule to EVMS Schedule and Metrics

机译:EVMS日程和指标的赚取的时间表比较

获取原文
获取原文并翻译 | 示例
       

摘要

This paper summarizes an analysis of a comparison between standard EVMS metrics and an Earned Schedule (ES) approach, to see if use of ES would provide more meaningful forecasting data versus conventional EVMS analyses. Seven facilities were initially selected for this analysis, which are part of a large waste treatment facility complex being built by the U.S. Government in the Pacific Northwest. These facilities were under-going engineering, procurement, and construction (EPC) during calendar years 2002 to 2012. Initial analysis indicates that the ES metrics for the EPC portion of the facilities - which range in price from about $4 to $19 million - appear to provide a meaningful indication of the schedule variance in terms of months, especially towards the end of a project. It was found, though, that sometimes the ES metric can overstate the actual progress. An anticipated direct comparison to the actual corresponding schedules was not able to be made, so a review of some time-based Independent Estimate at Completion metrics was conducted.
机译:本文总结了对标准EVMS指标与赚取的时间表之间的比较分析,看看ES的使用是否会提供更有意义的预测数据与常规EVM分析。最初选择了七种设施进行此分析,这些分析是由美国政府在太平洋西北部建造的大型废物处理设施复合物的一部分。这些设施在2002年至2012年历年期间出现了进展的工程,采购和建设(EPC)。初步分析表明,EPC部分的ES指标 - 价格从约4%到1900万美元的价格根据月份,特别是在项目结束时提供有意义的时间表方差的指示。但是,它被发现,有时ES指标可以夸大实际进展。预计与实际相应的时间表的直接比较无法进行,因此对完成指标进行了一些基于时间的独立估计的审查。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号