Accuracy of FEL 2 Estimates in Process Plants

机译:工艺厂中FEL 2估计的精度

获取原文
获取原文并翻译 | 示例
           

摘要

Estimators use a variety of practices to determine the cost of capital projects at the end of the select stage when only a small portion of engineering is complete. The expected accuracy of these conceptual estimates is usually quoted at plus or minus 30 percent. However, many projects finish with costs outside that range. AACE International recommends that projects have a class 4 estimate when upwards of 15 percent of engineering is complete, which is approximately the end of the select phase. Data from actual projects in the process industries show that conceptual estimates labeled as class 4 are not as predictable as expected. In fact, most class 4 estimates resemble the predictability of class 5 estimates. Given this, the question that follows is: What drives variance in performance measured from the FEL 2 estimates? Using Independent Project Analysis's (IPA's) extensive database, the author looked at project estimates and practices to identify approaches that improve the accuracy of FEL 2 estimates.
机译:估算器使用各种实践来确定选择阶段结束时的资本项目成本,只有一小部分工程完成。这些概念估计的预期准确性通常以加号或减去30%引用。但是,许多项目在该范围之外完成了成本。 AACE INTERNATIONAL建议,当工程的向上完成15%的速度时,项目有一个4级估计,这大约是选择阶段的结束。来自过程行业的实际项目的数据表明,标记为4类的概念估计并不像预期的那样可预测。事实上,大多数4类估计类似于5类估计的可预测性。鉴于这一点,如下所示是:从FEL 2估算中测量的性能方差是什么?使用独立的项目分析(IPA)的广泛数据库,提交人查找项目估计和实践,以确定提高FEL 2估计准确性的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号