Reline of Gwangyang No.3 Blast Furnace

机译:光阳号3号高炉的Reline

获取原文
获取原文并翻译 | 示例
           

摘要

Blast furnaces in Gwangyang have been produced 250 million tons of hot metal for 20 years since the first tap of No.1 blast furnace in 1987. Since the reline of No.1 furnace in 2002, No.2 furnace was relined in 2005 and No.3 in 2007 with increased furnace volume. The reline construction periods had been decreased as follows; G1R1-99 days, G2R1-66 days, G3R1-55 days without using large block method. The reline of No.3 blast furnace was done from 6 Oct ~ 29 Nov of 2007, which has produced 13,933T/m3(I.V) during the fist campaign for 16 years and 10 months.
机译:灯阳厂的高炉已经生产了2.5亿吨的热金属20年,自1987年第一间高炉首次点击。由于2002年的第1炉Reline,2005年的No.2炉子被重新着用,没有 .3 2007年,炉子量增加。 Reline施工期如下减少; G1R1-99天,G2R1-66天,G3R1-55天不使用大块方法。 3号高炉的Reline于2007年10月6日至29日开始,在拳头运动期间生产了13,933t / m3(i.v),持续16年和10个月。