A schedule constructability review is performed to analyze and assess the feasibility of the construction plan. These reviews are intended to bring to light problems in the following areas: reasonableness of work sequence, comprehensive and completion of construction planning, coordination and interface among the various craft trades and engineering disciplines, adequacy of lead time for material and equipment procurement, site work restrictions and adequacy of site access. The schedule constructability review compares the planned sequence of work with the project scope, site requirements, and the specific needs of the client. This presentation will focus on constructability concepts influencing the construction execution planning and a suggested review process for the construction project schedule.
机译:进行进度可施工性审查以分析和评估施工计划的可行性。这些审查旨在揭示以下领域的问题:工作顺序的合理性,施工计划的全面和完成,各种手工艺行业和工程学科之间的协调和衔接,材料和设备采购的提前期充足,现场工作网站访问的限制和充分性。进度表可建设性审查将计划的工作顺序与项目范围,现场要求和客户的特定需求进行比较。本演讲将重点讨论影响施工执行计划的可施工性概念以及对施工项目进度表的建议审查过程。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号