Start-up alternatives and performance of an UASB pilot plant treating diluted municipal wastewater at low temperature

机译:UASB中试设备的替代方案和性能,可在低温下处理稀释的市政废水

获取原文
获取原文并翻译 | 示例
           

摘要

Different start-up procedures of an upflow anaerobic sludge bed (UASB) digester were carried out. Start-up without inoculum (experiment A) was delayed for about 120 day. The digester reached 75-85% total suspended solids (TSS) removal, 54-58% total chemical oxygen demand (TCOD) removal and 63-73% biological oxygen demand (BOD5) removal at influent concentrations of 240-340 mg TCODi l(-1), temperatures of 13.5-15 degrees C and hydraulic retention times (HRT) of 10-11 h.
机译:进行了上流厌氧污泥床(UASB)消化池的不同启动程序。没有接种的启动(实验A)被推迟了大约120天。在进水浓度为240-340 mg TCOD11时,消化池的总悬浮固体(TSS)去除率为75-85%,化学需氧量(TCOD)去除率为54-8%,生物需氧量(BOD5)的去除率为63-73%。 -1),温度为13.5-15摄氏度,水力停留时间(HRT)为10-11小时。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号