A 450-foot-tall chimney at a lignite-coalfired power plant in Texas was blasted, cleaned, lined with insulating block for corrosion protection, and inspected, all with the aid of a powered float platform custom-designed for the job. The round platform, 31 feet in diameter, provided workers with close access to the interior wall of the plants stack. The lining work was performed at the newly constructed power plant from September 2008 through January 2009 and from March through June 2009.As of press time, the plant is "in commissioning" —producing electricity during test runs.
机译:得克萨斯州褐煤电厂的一个450英尺高的烟囱被喷砂,清洁,衬有绝缘块以防腐蚀,并在为该工作量身定制的电动浮平台的辅助下进行了检查。直径为31英尺的圆形平台使工人可以接近植物堆的内壁。衬砌工作是在2008年9月至2009年1月以及2009年3月至2009年6月期间在新建的发电厂进行的。截至发稿时,该发电厂正在“调试”中-在试运行中发电。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号