首页> 外文期刊>Water and Energy International >RIVER DIVERSION SCHEME CHAMERA HYDROELECTRIC PROJECT STAGE-II (3 X 100 MW)
【24h】

RIVER DIVERSION SCHEME CHAMERA HYDROELECTRIC PROJECT STAGE-II (3 X 100 MW)

机译:河流改道计划凯梅拉水电项目第二阶段(3 X 100 MW)

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

The diversion works in Chamera Hydroelectric Project Stage-II have been provided to divert the non-monsoon river flow whereas, during monsoon months, river was allowed to pass over partially constructed spillway blocks. The diversion scheme consist ofconstruction of upstream and downstream Cofferdams and about 300 m long 10.15 m (W) X 7.7 m (H) concrete lined (30 cm thick, M30 A20 grade) diversion tunnel with its inlet and outlet structures. Design discharge for the diversion tunnel was 592 cumec, which matched with 50 years return period for non-monsoon flow. With the designed arrangement, maximum velocity of water does not cross 12.60 m/s under any circumstances.
机译:Chamera水电项目第二阶段的引水工程已用于引流非季风河水,而在季风月份,河水被允许越过部分建造的溢洪道。导流方案包括上游和下游围堰的建造以及约300 m长的10.15 m(W)X 7.7 m(H)衬砌(30厘米厚,M30 A20级)混凝土导流隧道及其进水口和出水口结构。引水隧洞的设计流量为592立方公尺,与非季风流量的50年回收期相匹配。采用设计的布置,在任何情况下,最大水流速度都不会超过12.60 m / s。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号