Operating Results for the Tray Absorber Installed by Babcock Noell GmbH at the Oxyfuel Pilot Plant at the Site of Schwarze Pumpe and Tray Retrofitting in Existing Plants

机译:由Babcock Noell GmbH在Schwarze Pumpe现场的Oxyfuel中试工厂安装的塔盘吸收器的运行结果以及现有工厂的塔盘改造

获取原文
获取原文并翻译 | 示例
       

摘要

The Vattenfall Europe Generation AG built at its Power Plant site Schwarze Pumpe a 30 MW pilot boiler plant for the purposes of testing a CO_2-free power plant based on the oxyfuel procedure. The Babcock Noell GmbH was commissioned with the task of constructing the FGD. This plant was put into operation in the middle of 2008 and the acceptance measurements were carried out between 27th and 30th October 2008. A pilot operation, which is set to span several years, should now provide values based on experience for the various plant parts and components which are used in the flue gas cleaning plant.
机译:Vattenfall欧洲发电公司在其发电厂站点Schwarze Pumpe上建造了30兆瓦的中试锅炉厂,目的是根据含氧燃料程序测试无CO_2的发电厂。 Babcock Noell GmbH受委托建造烟气脱硫装置。该工厂于2008年中投入运营,并于2008年10月27日至10月30日进行了验收测试。该试验项目定于数年之内,现在应根据工厂各个部分的经验提供价值。烟气净化设备中使用的组件。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号