New boiler construction at Lunen Power Station within an extremely short time-scale

机译:在很短的时间内在鲁嫩电站建设新锅炉

获取原文
获取原文并翻译 | 示例
获取外文期刊封面目录资料

摘要

As a result of a fault on 25 October 1994, the boiler plant of the 150 MW unit at Lunen Power Station had to be completely demolished and subsequently constructed anew. In this process, the two-pass boiler with slag-tap pulverised coal firingaffected by the incident was replaced by a tower-type boiler with dry-bottom firing. From the date of order to guaranteed steam supply, less than only 19 months elapsed. An adequate pre-planning period and recourse to standardised pre-designed moduleswere decisive for such a short completion period.
机译:由于1994年10月25日的故障,鲁嫩电站150 MW机组的锅炉厂必须完全拆除,然后重新建造。在此过程中,事故引起的炉渣粉煤燃烧的二程锅炉被干底燃烧的塔式锅炉所取代。从订购之日到保证的蒸汽供应,不到19个月就过去了。对于如此短的完成时间,决定性的是有足够的预计划时间和采用标准化的预先设计的模块即可。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号