Hokkaido Electric Power Co. will delay restart of Unit 4 at Tomato-Atsuma Power Plant. The unit is a coal-firedfacility with 700 MW.Unit 4 ceased power generation at 3:20 am on February 6 due to the steam leakage out of boiler. After replacingdamaged parts, Hokkaido had announced that the unit would resume by February 26. In fact, the repair work of boiler isalready done.