GUANGDONG GUANHAO HITS DELAY WITH NEW COATER

机译:广东冠豪新涂层机延后

获取原文
获取原文并翻译 | 示例
       

摘要

China's Guangdong Guanhao High Tech has postponed the startup of a 60,000-tonne/yr coating line at a greenfield plant in Zhanjiang city, Guangdong province, due to delays with deliveries of auxiliary equipment. The firm has pushed back trial runs, which were originally scheduled to kick off in December, to July this year. Commercial production is expected to follow two months later.
机译:由于延迟交付辅助设备,中国广东冠豪高​​科技有限公司已推迟在广东湛江市的一个新建工厂启动一条年产6万吨/年的涂层生产线。该公司已将原定于12月开始的试运行推迟到今年7月。预计两个月后将进行商业生产。