Five years of operating experience at a large, utility-scale photovoltaic generating plant

机译:在大型公用事业规模的光伏发电站五年的运营经验

获取原文
获取原文并翻译 | 示例
           

摘要

Tucson Electric Power Company (TEP), headquartered in Tucson, AZ, currently has nearly 5.0 MWdc of utility-scale grid-connected photovoltaic (PV) systems installed in its service territory. These systems have been installed through a multiyear, pay-as-you-go development of renewable energy, with kWhac energy production as a key program measurement. This PV capacity includes a total of 26 crystalline silicon collector systems, each rated at 135 kWdc for a total of 3.51 MWdc, that have been installed at the Springerville, AZ generating plant by TEP making this one of the largest PV plants in the world. This facility started operations in 2001 and recently passed the 5-year milestone of continuous operations. These systems were installed in a standardized, cookie-cutter approach whereby each uses the same array field design, mounting hardware, electrical interconnection, and inverter unit. This approach has allowed TEP to achieve a total installed system cost of
机译:总部位于亚利桑那州图森的图森电力公司(TEP)目前在其服务区域内安装了将近5.0 MWdc的公用事业规模并网光伏(PV)系统。这些系统是通过多年的,按需购买,按需购买的可再生能源开发安装的,其中kWhac能源产量是关键的计划衡量指标。该光伏发电容量包括26个晶体硅集热器系统,每个额定功率为135 kWdc,总功率为3.51 MWdc,TEP已将其安装在亚利桑那州Springerville的发电厂中,这使其成为全球最大的光伏发电厂之一。该工厂于2001年开始运营,最近通过了连续运营5年的里程碑。这些系统以标准化的切饼机方法安装,因此每个系统都使用相同的阵列现场设计,安装硬件,电气互连和逆变器单元。这种方法使TEP的总安装系统成本达到了

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号