FERC approves 34-mile Sunbury pipeline that will deliver Marcellus gas to Pa. plant

机译:FERC批准了34英里的Sunbury管道,该管道将将Marcellus天然气输送至宾夕法尼亚州的工厂

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

The Sunbury Pipeline Project, which will move about 200 MMcf/d of Marcellus gas from interstate pipelines to a new power plant and local gas distribution in northeastern Pennsylvania by February 2017, was granted a Federal Energy Regulatory Commission certificate approving the project on April 29. Approval of the 34-mile, 20-inch diameter greenfield project was about four months later than the company had requested. However, there have not been any updates to the project’s timeline. Information on the construction schedule and anticipated in-service date will likely become available in the coming weeks as Sunbury moves forward with an implementation plan.
机译:Sunbury管道项目将于2017年2月之前将约200 MMcf / d的Marcellus天然气从州际管道输送到新的电厂,并在宾夕法尼亚州东北部的当地天然气配送,该项目于4月29日获得了联邦能源管理委员会的批准。这个直径34英里,直径20英寸的未开发项目的批准比该公司的要求晚了大约四个月。但是,该项目的时间表没有任何更新。随着Sunbury推进实施计划,有关施工时间表和预计启用日期的信息可能会在未来几周内获得。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号