LES MOUVEMENTS DES TERRES DE LA LGV SUD EUROPE ATLANTIQUE (SEA)

机译:南大西洋欧洲HSL(SEA)的陆运

获取原文
获取原文并翻译 | 示例
获取外文期刊封面目录资料

摘要

The SEA project has been the biggest civil engineering project in recent years with regard to earthworks. The length of subgrade to be executed is 340 km, including 38 km of connections to the existing railway network, representing a total of 70 million cu.m. The priority assigned to compliance with deadlines (just after the absolute priority assigned to workplace safety) resulted in a rather atypical project management system, focused on decentralisation of each section of the design engineering, production and external inspection activities. This priority, together with very thorough preparation, made it possible to comply with the original deadlines so as to lay the first rails on standard sections and perform all earthworks in two-and-a-half years (April 2012 -autumn 2014).%LE PROJET SEA, AUJOURD'HUI LE PLUS GROS PPP FERROVIAIRE DU MONDE, EST AUSSI LE PLUS IMPORTANT CHANTIER DE GÉNIE CIVIL D'EUROPE DE CES DERNIÈRES ANNÉES. LE PRÉSENT ARTICLE DÉCRIT LA RÉALISATION DES TERRASSEMENTS PAR LE SOUS-GROUPEMENT INFRASTRUCTURES (SGI) DU CONCEPTEUR-CONSTRUCTEUR COSEA. LE LINÉAIRE DE PLATE-FORME À RÉALISER S'ÉLÈVE À 340 KM, DONT 38 KM DE RACCORDEMENTS AU RÉSEAU FERRÉ EXISTANT, REPRÉSENTANT AU TOTAL 70 MILLIONS DE M3 DE TERRASSEMENT. L'ENSEMBLE DES TRAVAUX DE TERRASSEMENT A ÉTÉ RÉALISÉ EN 2 ANS ET DEMI (AVRIL 2012 - AUTOMNE 2014) AVEC UN PHASAGE TRÈS SERRÉ LIÉ À L'ENCHAÎNEMENT AVEC LES TRAVAUX FERROVIAIRES.
机译:SEA项目是近年来有关土方工程的最大土木工程项目。待执行的路基长度为340公里,包括与现有铁路网的38公里连接,总计为7,000万立方米。遵守截止日期的优先级(紧随分配给工作场所安全的绝对优先级之后)导致了一个非典型的项目管理系统,其重点是分散设计工程,生产和外部检查活动的各个部分。这一优先事项以及非常周密的准备工作,使其有可能遵守原定的截止日期,以便在两年半的时间内(2012年4月至2014年秋季)在标准路段铺设第一条滑轨,并进行所有土方工程。% LE PROJET SEA,AUJOURD'HUI LE PLUS GROS PPP FERROVIAIRE DU MONDE,EST AUSSI LE PLUS重要的CHANTIER DEGÉNIECIVIL D'EUROPE DE CESDERNIÈRESANNÉES。概念建筑COS LE的法国苏黎世大学论文集。 LELINÉAIREDE PLATE-FORMEÀRÉALISERS'ÉLÈVEÀ340公里,Dont 38 KM残迹AURÉSEAUFERRÉ现有,代表总计7000万DE M3 DE露台。 L'ENSEMBLE DES TRAVAUX DE TERRASSEMENT AÉTÉRÉALISÉEN 2 ANS ET DEMI(AVRIL 2012-AUTOMNE 2014)AVEC UN PHASEAGETRÈSSERRÉLIÉÀL'ENCHAPLANEMENT AVEC LES TRAVAUX FERROVIAIRES。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号