Case study of Marquette-Lez-Lille WWTP: application of IFAS and THP for a city of the future

机译:Marquette-Lez-Lille污水处理厂案例研究:IFAS和THP在未来城市中的应用

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

The Lille metropolitan area awarded Veolia Water the contract to reconstruct the Marquette-lez-Lille wastewater treatment plant (WWTP) in 2010, the biggest such facility in the north of France. The capacity of the new WWTP is 700,000 m³/day, serving a population of 620,000. It will be built on the site of the previous one, which is now obsolete.The renovation work comprises four treatment lines, including wastewater, stormwater sludge treatment lines, and a deodorization line. By applying state-of-the-art design and proven technologies, especially Hybas™ and Exelys™-DLD, a sustainable development solution was provided to local communities.The effluent from the new plant will meet the requirements of the European Water Framework Directive (Directive 2000/60/EC) on ‘good ecological status’ of water, and the treated storm water will be used to irrigate 7 hectares wetland. Compared with conventional digestion, the Exelys™-DLD configuration will further reduce sludge quantities by 30% and increase biogas production by 20%. Thereby, 94% of the power requirements will be supplied from the plant itself.The water line started operating in February 2013, and commissioning of the sludge line, which started in July 2014, was expected to finish in February 2015. In this paper, the design concept of the sustainable development solution is presented, as well as the application of showcase technologies for wastewater and sludge treatment.
机译:里尔市辖区授予威立雅水务公司一份合同,以在2010年重建Marquette-lez-Lille废水处理厂(WWTP),这是法国北部最大的污水处理厂。新的污水处理厂的日处理能力为700,000立方米/天,为62万人口提供服务。它将在以前的旧站点上建造,现在已经过时了。改造工作包括4条处理线,包括废水,雨水污泥处理线和除臭线。通过采用最先进的设计和成熟的技术,尤其是Hybas™和Exelys™-DLD,为当地社区提供了可持续发展解决方案。新工厂的废水将满足欧洲水框架指令(关于水的“良好生态状态”的指令2000/60 / EC),经过处理的雨水将用于灌溉7公顷的湿地。与传统的消化相比,Exelys™-DLD配置将进一步减少30%的污泥量和20%的沼气产量。因此,其中94%的电力需求将由工厂本身提供。供水管线于2013年2月开始运行,污泥管线的调试于2014年7月开始,预计于2015年2月完成。介绍了可持续发展解决方案的设计概念,以及展示技术在废水和污泥处理中的应用。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号