首页> 外文期刊>Trenchless Technology >DC WATER B STREET NEW JERSEY AVENUE TRUNK SEWER
【24h】

DC WATER B STREET NEW JERSEY AVENUE TRUNK SEWER

机译:DC WATER B STREET新泽西州大道干杯

获取原文
获取原文并翻译 | 示例

摘要

The observations from the visual inspection, results of the non-destructive testing, and output from the structural modeling identified areas with multiple crown cracks and areas where the bond strength at the construction joint has been significantly reduced as the most critical defects that could potentially compromise the structural integrity of the sewer. Based on this prioritization, it is recommended that these areas be considered for immediate repair. Locations where the concrete at the construction joint was observed to have "turned to gravel" or where it was described as "too soft" are slightly more ambiguous because non-destructive testing results could not be obtained for these areas. However, visual observations identified deterioration of the concrete that could result in a reduction in bond strength at the construction joint. Because these areas do not display roots and water infiltration, and inspectors were not able to push the probing rod partially through the concrete, these areas are classified as less significant than the top priority side wall defects. The structural modeling did not identify areas with multiple defects as a critical condition. However, the presence of multiple deficiencies could indicate conditions, such as settlement, high groundwater elevations, or unbalanced external loads, which are causing higher stress levels in these sections of sewer. Therefore, these areas should be monitored and considered for repair after the top priority issues have been addressed. Other defects were observed during testing at varying levels of severity. However, these areas were not determined to be a priority for repair based on structural modeling. The visual observations and non-destructive testing results also did not identify these areas as critical. Although these areas are not identified as requiring repair at this time, it is recommended that they continue to be monitored and compared to the baseline conditions established by this inspection. If conditions are observed to change, they should be reprioritized as appropriate. Follow-up visual inspections are recommended at intervals of approximately every 5 years to monitor existing conditions.
机译:目视检查的观察结果,非破坏性测试的结果以及结构模型的输出确定了具有多个冠状裂纹的区域以及施工缝处的粘结强度已大大降低的区域,因为这是最有可能危害的最关键缺陷下水道的结构完整性。基于此优先顺序,建议考虑立即修理这些区域。观察到施工缝处的混凝土“变成砾石”或被描述为“太软”的位置更加模糊,因为无法获得这些区域的无损检测结果。但是,目视观察发现混凝土的变质可能会导致施工缝处粘结强度降低。由于这些区域没有根部和水的渗透,并且检查员无法将探测棒部分推入混凝土,因此这些区域的重要性不如最重要的侧壁缺陷。结构建模未将具有多个缺陷的区域确定为关键条件。但是,多种缺陷的存在可能表明诸如沉降,高地下水位或外部负载不平衡之类的状况,这些状况导致下水道这些部分的应力水平更高。因此,在解决了最重要的问题之后,应对这些区域进行监控并考虑进行维修。在测试过程中,以不同级别的严重性观察到其他缺陷。但是,根据结构建模,这些区域并没有确定为修复的优先重点。目视观察和非破坏性测试结果也未将这些区域确定为关键区域。尽管此时尚未确定这些区域需要维修,但建议继续对其进行监视,并将其与本次检查确定的基准条件进行比较。如果发现情况发生了变化,则应适当地重新设置优先级。建议以大约每5年一次的间隔进行目视检查,以监视现有状况。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号