Quantitative Comparison of Project Performance between Project Delivery Systems

机译:项目交付系统项目性能的定量比较

获取原文
获取原文并翻译 | 示例
           

摘要

A project delivery system (PDS) defines the relationship and timing of involvement between different contracting parties in construction. Using data from 109 projects, this paper statistically investigates the project performance of the four main PDSs: design-bid-build (DBB), construction management (CM), design-build (DB), and integrated project delivery (IPD). First, descriptive statistical methodologies were applied to the dataset to determine performance benchmarks for each examined PDS. Next, by applying statistical tests, such as the analysis of variance (ANOVA) F-test and the Kruskal-Wallis H-test, statistically significant performance differences among the examined PDSs were identified in five performance areas: cost, schedule, quality, communication, and change management. Finally, pairwise comparisons were performed by applying posthoc statistical tests to each pair of PDSs, demonstrating that IPD outperformed DBB in 11 metrics, while it outperformed CM and DB in two metrics each. Also, DB outperformed DBB in seven metrics, and CM outperformed DBB in five metrics. This paper addresses a consistently missing piece in the existing body of literature related to project delivery. The findings presented in this paper should prompt industry leaders and professionals to move away from the DBB model and toward IPD and other synergic PDSs. (c) 2020 American Society of Civil Engineers.
机译:项目交付系统(PDS)界定了建设中不同缔约方之间参与的关系和时间。本文使用来自109个项目的数据,统计研究四个主要PDS的项目性能:设计 - 出价(DBB),施工管理(CM),设计 - 构建(DB)和集成项目交付(IPD)。首先,将描述性统计方法应用于数据集以确定每个检查的PD的性能基准。接下来,通过应用统计测试,例如差异分析(ANOVA)F检验和Kruskal-Wallis H-Test,在五个性能领域确定了检查的PDS中的统计学上显着的性能差异:成本,进度,质量,沟通和改变管理。最后,通过将POSTHOC统计测试应用于每对PDS的POSTHOC统计测试来执行成对比较,展示IPD在11个指标中表现出IPD,而在每个度量标准中表现优于CM和DB。此外,DB优于七个度量标准的DBB,CM在五个度量中表现优于DBB。本文涉及与项目交付相关的现有文学体系持续缺失的作品。本文提出的调查结果应促使行业领导者和专业人员远离DBB模型以及IPD和其他协同PDS。 (c)2020年美国土木工程师协会。

著录项

  • 来源
    《Journal of Management in Engineering》 |2020年第6期|04020082.1-04020082.13|共13页
  • 作者单位

    Calif State Univ Los Angeles Construct & Engn Management Dept Civil Engn E&T A-215 5151 State Univ Dr Los Angeles CA 90032 USA;

    Univ Wisconsin Dept Civil & Environm Engn Construct Engn & Management Program 2320 Engn Hall 1415 Engn Dr Madison WI 53706 USA;

    Boldt Co 2525 Roemer Rd Appleton WI 54912 USA;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号