Horizontal Rotation via Floatation as an Accelerated Bridge Construction for Long-Span Footbridge Erection: Case Study

机译:通过浮动水平旋转作为大跨度人行桥架设的加速桥梁施工:案例研究

获取原文
获取原文并翻译 | 示例
       

摘要

The new Father Bernatek footbridge (pedestrian bridge) over the Vistula River opened in 2010 in Cracow, Poland, is a 148-m-long tied fixed arch steel structure with one main tubular arch of circular cross section and twin suspended orthotropic steel decks. The most challenging part of the project was the accelerated bridge construction (ABC), i.e., assembly and erection as a tied arch. The river was allowed to be closed for the minimum time possible during the construction process because it also serves as a navigation channel for the tourist fleet and other river traffic. Therefore, it was decided to assemble the entire superstructure on the south bank of the river and to launch it by 90 degrees rotation via floatation on barges with the river current upstream as a single rigid body. The applied ABC method allowed preparation and performance of the bridge construction in the most effective and efficient way and in the shortest possible time. The superstructure rotation method (SRM) with the most efficient, sustainable use of resources and with minimum disturbance and disruption for the urban environment and the inhabitants was applied. The paper briefly describes the new footbridge and the rarely selected ABC technology used for its erection, i.e., horizontal rotation via the floatation SRM method. Useful references describing the SRM construction method, which is a useful ABC solution for bridges throughout the world, are provided. This signature span is now a popular destination for citizens and tourists. (C) 2014 American Society of Civil Engineers.
机译:波兰克拉科夫的维斯杜拉河上的新的贝纳泰克神父人行天桥(人行天桥)于2010年在波兰克拉科夫启用,是一座148米长的固定式固定拱形钢结构,具有一个圆形横截面的主管状拱形和双悬正交异性钢甲板。该项目最具挑战性的部分是加速桥梁建设(ABC),即作为拱门的装配和架设。在建设过程中,允许将河流关闭的时间尽可能短,因为它也可以作为游客车队和其他河流交通的导航通道。因此,决定在河南岸组装整个上层建筑,并通过在驳船上漂浮而将其上游旋转,将上游河水作为单个刚体以90度旋转的方式发射。应用的ABC方法可以以最有效,最有效的方式并在最短的时间内准备和执行桥梁施工。采用了最有效,可持续地利用资源,对城市环境和居民造成最小干扰和破坏的上层建筑旋转方法(SRM)。本文简要介绍了新的行人天桥和很少使用的ABC技术来架设它,即通过浮动SRM方法进行水平旋转。提供了有用的参考文献,描述了SRM构造方法,这是一种适用于世界各地桥梁的ABC解决方案。这个标志性跨度现已成为市民和游客的热门目的地。 (C)2014年美国土木工程师学会。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号